How to physically install the ClickShare Control Panel?

Article number: [15486]

Applicable to

Overview

This article explains how to physically install the ClickShare Control Panel. It is the next step after setting up the USB-C cable connection with the Control Panel. Click here to view the connection setup process.

Installation options include:

Required tools:

  • Screwdriver and nut driver
  • Components included in the packaging box with Control panel
    • Round stand
    • L-shaped bracket
    • Short screws (2 nos.)
    • Long (M4) screws (2 nos.)
    • Washers (2 nos.)
    • Nuts (2 nos.)

How to install standing on a table with the round stand

  1. Install the round stand (A) on the Control Panel. Use the two short screws (1).

  2. Place the assembled Control Panel in a desired location on the table.

  3. Connect the ‘Source’ side of the cable (C) to the Base Unit.



How to secure to a table in the upright position

  1. Drill two holes in the table at the desired location. Ensure the holes are spaced 34mm apart.

  2. Install the L-shaped bracket (B) in the desired location on the table. Use the two long screws (2), two washers (3) and two nuts (4).

  3. Install the Control Panel onto the prepared base as illustrated. Use the two short screws (1).

  4. Connect the ‘Source’ side of the cable (C) to the Base Unit.



How to secure to a table in the flat position

  1. Drill two holes in the table at the desired location. Ensure the holes are spaced 34mm apart.

  2. Install the L-shaped bracket (B) in the desired location on the table. Use the two long screws (2), two washers (3) and two nuts (4).

  3. Install the Control Panel onto the prepared base as illustrated. Use the two short screws (1). Ensure the rubber strip (Z) makes contact with the table.

  4. Connect the ‘Source’ side of the cable (C) to the Base Unit.



How to secure to a wall

  1. Drill two holes in the wall at the desired location. Ensure the holes are spaced 34mm apart.

  2. Install the L-shaped bracket (B) to the wall. Provide two M4 screws at least 25.4mm long (**).

  3. Install the Control Panel on the secured L-shaped bracket (B). Use the two short screws (1). Ensure the rubber strip (Z) makes contact with the wall.

  4. Connect the ‘Source’ side of the cable (C) to the Base Unit.